Anyway.... progress.
Wall foundations are in.....
New temporary stairs configuration for access to the back/bathroom (yes it is slightly wonky)
False walls are being constructed around the juliet balcony doorway....
Thats all great stuff. They did forget to put the helifix bars into the wall with the crack (to hold up the back of the house!) but they are just taking off the plasterboard and putting them in.
The joists in the new corridor where the small v-lux windows will go.....Unfortunately Virgus (our foreman)noticed that we had ordered V-lux windows 78cm across and the corridor is actually 71cm across. So we will have to have new ones delivered.
The holes in the bathroom roof for the big windows, more V-lux's....
The wet-room area in the bathroom......
The new corridor.....
And some pictures of the state of the rest of the house in the meantime....this is where work has not started, or is in early stages. It is v. messy, and v. dusty.